Step 2: What to include in your permit
Required documentation
May include but is not limited to the following:
- Site Specific Safety Plan (SSSP)
- Environmental Management Plan
- Safe Work Method Statement (SWMS)
- Site Layout Plan
- Public Liability Insurance
- Plant, machinery and tools used
- Rail Competencies
1) Health and Safety Plan: A tailored health and safety plan must be submitted, approved, and endorsed by the commissioning entity, which may include the primary contractor. This plan should encompass:
-
A Risk Register identifying potential hazards within the rail corridor.
-
A comprehensive list of locations pertinent to the permit.
-
An Emergency Response Plan, including the procedure for contacting the KiwiRail emergency line at 0800 808 400.
-
A designated Incident Reporting Protocol for any occurrences within the rail corridor.
-
Evidence of WorkSafe Notification for works classified as “Notifiable”.
-
A detailed Communication Strategy for the worksite, covering radio frequencies and essential contact details.
-
Environmental Management Plan: Outline your strategy for managing environmental impacts.
2. Work Methodology: Provide a statement detailing your approach to safe work practices, such as a Safe Work Method Statement.
3. Site Documentation: Submit a site or layout plan along with photographs detailing the proposed work area.
4. Insurance Certification: A Public Liability Insurance Certificate for $10 million is required. Certificates must be provided by the permit applicant, the main contractor, and any subcontractors involved.
5. Equipment Details: List all machinery and tools that will be utilized.
6. Traffic Management Plan: Necessary if work activities are within 100 meters of a level crossing.
7. Crew Competency Verification: Provide the names and KiwiRail Learning Exchange (KLE) customer numbers for all crew members to confirm their rail-specific qualifications. Visit training and inductions for more information.