Mana summer works
This summer KiwiRail will be renewing railway line at Mana between Paremata and Mana Stations. We will also be working near Porirua Station.
Status: Upcoming
- Start date –
- Finish date –
This summer KiwiRail will be relaying track on the Kapiti Line between Paremata Station through to north end of Mana Station. This is an important part of keeping your Wellington Metro up-to-date and reliable.
Project set-up begins 21 December, with the main works getting underway 26 December through to Monday 11 January 2027. The main works will involve both day and night work. Clean up work will continues between 11 and 15 January 2027.
You can expect to see extra truck movements through Pascoe Avenue, and through the Mana and Paremata Station carpark areas. There will be reduced parking at the Mana Rugby Club, Mana Marina, and Mana Station car parks, and Paremata Station.
Last updated: